help

Grand Launching of NIBT eLearning with 50% Slash Down on Course & Package Fee *Limited Time Offer Grab Discount!

Toll Free: 1800 200 1955

Case Studies

MEP BIM Modeling and Clash Detection for Plant Room of College Campus Building Based in Europe


The Objective

The Team Created 3D architecture and structure layout in Revit MEP and allocated mechanical equipment with connection for a clash free model.Technology/Software Used

Revit

Challenges

  • A detailed plant room with all the spatial information, equipment and connections had to be developed from general arrangement drawings and a set of pdf files with manufacturing details of the MEP equipment.
  • The process henceforth involved clash detection, reporting and resolutions. Finally clash free models, rendered images and shop drawings had to be delivered in a time span of 3 months.

Engineering Solution

  • MEP designs and general arrangement drawings were thoroughly examined
  • Basic 3D architecture and structure layout was created in Revit MEP
  • Mechanical equipment with detailed connections and well arranged clash free model as per provided inputs was prepared
  • In addition to Revit MEP Plant rooms and shop drawings, sheet setup and 3D rendering as required was also developed and handed over to client

Benefits

  • The project was successfully executed and handed over within the specified time frame of 3 months.
  • Initially the contract was on project basis. As client was satisfied with the quality produced, he has opted for full time resource business model and a long term partnership was built.

Https://thebimhub.com/2016/04/20/mep-bim-modeling-and-clash-detection-for-plant-roo/#.WNjHlG996Uk

Similar Case Studies

VIETNAM BIM PROJECT CASESTUDY: VIETINBANK TOWER



Read More >

AG5 Uses AECOsim Building Designer for Comprehensive Building Information Modeling



Read More >

BIM coordinate for The Landmark 81 Building



Read More >

You Can Call Us On Toll Free No.: 1800 200 1955